Development

3663 MWp

Early Stage

353 MWp

Middle Stage

271 MWp

Advanced Stage

39 MWp

RTB

Looking to the future now more than ever before

At ID Energy, we are specialists in solar photovoltaic energy. We support our clients throughout all stages of the process, from identifying opportunities and developing projects through to construction and maintenance, allowing them to avoid risks and providing a committed, agile and approachable service.

<50%

Early Stage

Connection point requested or connection approved by the distributor.

>50%

Middle Stage

Access and connection point granted and prior administrative authorization submitted, in addition to the environmental impact assessment (EIA) when applicable.

>80%

Advanced Stage

Project close to RTB status, with prior administrative authorisation and construction authorization approved or close to approval.

100%

Under Construction

Project construction under way or scheduled to begin soon.

.

IPP Operation

Project constructed and supplying the grid.

Early Stage (MWp) Advance Development (MWp) Backlog (MWp) Under Construction (MWp) IPP Operation (MWp) Total (MWp)
Hungary 258 151 27 5 11 452
Poland 605 565 30 2 0 1,202
Spain 902 774 17 13 0 1,706
Serbia 0 25 0 0 0 25
TOTAL 1,765 1,515 74 20 11 3,384